Since 1 Apr 2025 Slovakia has a new Building Act - the building permit (stavebné povolenie) was replaced by a building intent decision and project verification. An amendment follows on 1 Jan 2027. We explain what you need for a house, garage, fence or flat renovation, what it costs and how long it takes. Every rule is linked to the law.

Building permit in Slovakia 2026: building intent, notification, final approval and 2027 changes

What changed - a building intent instead of a building permit

The old Building Act No. 50/1976 Zb. applied for almost 50 years. The new Act No. 25/2025 Z. z. has been in force since 1 April 2025 and changes the whole procedure:

  • One procedure instead of two. The zoning decision and the building permit are no longer two separate proceedings. A single decision on the building intent sites and authorises the structure; the office then verifies the project with a verification clause (overovacia doložka) (§ 18 ods. 2, § 65).
  • New terms. Zoning proceedings (územné konanie) = building intent proceedings, building proceedings (stavebné konanie) = verification of the building project, final approval proceedings = final approval (kolaudácia) (§ 84 ods. 11).
  • Final approval certificate. The final approval decision (kolaudačné rozhodnutie) was replaced by a final approval certificate (kolaudačné osvedčenie) (§ 67).
  • The building office is the municipality. It is delegated state administration; municipalities may run a joint office (spoločný obecný úrad) (§ 15).
  • Electronically. Documentation is prepared and stored in the information system of the Office for Spatial Planning and Construction (§ 8 ods. 3); the application is filed electronically on the prescribed form (§ 50 ods. 1).
  • Opinions first. The builder or designer obtains the binding opinions of authorities and utility operators (záväzné stanoviská) before filing the application (§ 20).

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Portál výstavby (Office for Spatial Planning and Construction of the SR)

Three regimes: building intent, notification, no permit

Decision on the building intent

For what
new structures (incl. a family house), extensions, added storeys, larger structures; everything the law does not exempt
Documentation
building intent and building project by an authorised designer
Office deadline
30 / 60 / 90 days
Final approval
yes
Fee
family house: €300 + verification €90 - 150 + final approval €90

Notification (ohlásenie)

For what
minor structures and building alterations under the conditions of § 18 ods. 3 and structures under § 18 ods. 4
Documentation
building project for notification
Office deadline
30 days, then "tacit consent"
Final approval
no (with exceptions)
Fee
€50 (minor structure), €150 (alteration of a residential building)

Nothing needed

For what
routine maintenance, replacing fixtures and built-in furniture, other minor structures and alterations (§ 18 ods. 5)
Documentation
-
Office deadline
-
Final approval
no
Fee
€0

Minor and simple structure

  • Minor structure (drobná stavba). Cannot significantly affect its surroundings: mainly single-storey structures up to 50 m² and 5 m high (shed, summer kitchen, carport, sauna, garage), underground structures up to 25 m² and 3 m deep (cellar, cesspit, pool), fencing, utility connections (§ 2 ods. 4; from 2027 § 2 ods. 7).
  • Simple structure (jednoduchá stavba). Has no major impact on its surroundings: mainly a residential building with at most 3 flats, a built-up area up to 300 m² and at most 2 above-ground storeys (+ a basement and an attic) - i.e. an ordinary family house; a holiday cottage up to 300 m² with one above-ground storey; a retaining wall up to 3 m (§ 2 ods. 6).
  • Self-build. You can build a simple structure yourself (svojpomoc) - see the conditions in the self-build section below.

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027), Act No. 145/1995 Z. z. on Administrative Fees (položka 59)

What do I need for…

Family house (up to 3 flats, 300 m²)

Until 31 Dec 2026
building intent + project verification + final approval
From 1 Jan 2027
no change

Extension, added storey, attic conversion

Until 31 Dec 2026
building intent (change to a completed structure) + final approval
From 1 Jan 2027
no change

Garage, shed, summer kitchen up to 50 m²

Until 31 Dec 2026
always a notification
From 1 Jan 2027
notification if it has a solid foundation, stands closer than 2 m to the plot boundary or another condition of § 18 ods. 3 applies; otherwise nothing

Fence

Until 31 Dec 2026
notification if closer than 2 m to the plot boundary or next to a public space (minor structure up to 1.6 m opaque / 2 m see-through)
From 1 Jan 2027
the same, minor structure up to 2 m of any material

In-ground pool, cellar, cesspit up to 25 m²

Until 31 Dec 2026
notification
From 1 Jan 2027
notification (underground structure)

Flat renovation - tiles, floors, kitchen, bath, toilet, painting, windows

Until 31 Dec 2026
nothing
From 1 Jan 2027
nothing

Work on load-bearing structures, new openings in walls

Until 31 Dec 2026
notification; the office may require building intent proceedings
From 1 Jan 2027
the same; if building intent proceedings are required, final approval follows

Façade repair, roof covering replacement

Until 31 Dec 2026
nothing (unless it is a cultural monument)
From 1 Jan 2027
nothing; in a heritage area a notification if the appearance changes

Solar panels up to 50 kW

Until 31 Dec 2026
nothing
From 1 Jan 2027
nothing

Outdoor EV charging station

Until 31 Dec 2026
up to 22 kW: notification only if a condition of § 18 ods. 3 applies
From 1 Jan 2027
always a notification

The conditions of § 18 ods. 3 that trigger a notification: works in a public space, a structure closer than 2 m to the plot boundary, a structure with a registration number (súpisné číslo), a building with a solid foundation, an underground structure, a cultural monument, a heritage or protected area, a risk to health, structural stability or fire safety, a riverside plot, a floodplain or a water source protection zone. If unsure, ask the building office before you start.

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)

Building intent step by step

From the project to the final approval certificate - the usual order for a family house or an extension.

  1. The designer prepares the building intent

    For a family house this is an authorised designer (chartered architect or engineer); without a designer the office rejects the application (§ 59 ods. 1 písm. b)).

  2. Consultation on the intent

    The designer uploads the documentation to the information system and asks the spatial planning authority, the authorities concerned and the utility operators for binding opinions and statements. They have 30 days (60 for complex structures); if they miss the deadline, they are deemed to have no comments (§ 20, § 21 ods. 9). The result is the report on the consultation of the building intent (správa o prerokovaní).

  3. Application to the building office

    Electronically on the form, with the project documentation and the consultation report (§ 50). If anything is missing, the office asks you within 15 days to complete it (§ 50 ods. 3).

  4. Proceedings and decision

    Within 7 days the office notifies the owners of neighbouring plots and other parties that proceedings have started; objections can be raised at the latest at the oral hearing or, if there is none, within at least 7 working days (§ 49, § 51). The decision comes within 30 days if no hearing is needed, otherwise within 60 days (§ 58). The decision can be appealed within 15 days (§ 54 of the Administrative Procedure Code).

  5. Verification of the building project

    The office verifies the detailed project with compliance clauses (doložky súladu) within 30 days (§ 65). You can also submit the project together with the intent - it is then verified together with the decision, and the fee is lower.

  6. Construction

    The verified project and the construction log (stavebný denník) must be kept on site (§ 6 ods. 5); in the decision the office sets the stages at which it carries out a check inspection (§ 60 ods. 1 písm. g)). Construction must start within 2 years of the project's verification (§ 65 ods. 6).

  7. Final approval

    After completion you file an application for final approval and after the inspection receive the final approval certificate (§ 66, § 67). Only then may you use the house; after final approval, remember to file a property tax return.

Portál výstavby →

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 71/1967 Zb., Administrative Procedure Code (Správny poriadok), Portál výstavby (Office for Spatial Planning and Construction of the SR)

Notification of a minor structure or building alteration

  • What you file. A notification with the builder's details, land registry data on the plot and the type of works; attached are the building project for notification and the binding opinions of the authorities concerned (§ 63 ods. 2).
  • Who draws the project. It does not have to be an authorised designer - a person with a university degree in architecture, civil, mechanical or electrical engineering, or with secondary vocational education in these fields and at least 3 years of practice, is enough (§ 35 ods. 4, 5).
  • 30-day deadline. The office verifies the project with a clause or returns the notification. If it does nothing within the deadline, the clause is deemed issued (§ 63 ods. 6, 7).
  • The office may decide otherwise. If the structure would affect neighbours' rights or conditions need to be set, it tells you that building intent proceedings are required (§ 63 ods. 5).
  • Returned notification. A return can be challenged by a complaint (podnet) within 10 working days (§ 63 ods. 8).
  • Start within 3 years. The notified works must start within 3 years of the project's verification (§ 63 ods. 10).
  • No final approval. Final approval is generally not required for notified structures and alterations (§ 66 ods. 1).

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)

Fees 2026

ActFee
Decision on the building intent - family house (1 - 2 flats)€300
Decision on the building intent - simple non-residential structure (e.g. a larger garage)€300
Extension, added storey or demolition25% of the rate (family house €75)
Project verification together with the intent30% of the rate (family house €90)
Project verification separately50% of the rate (family house €150)
Notification of a minor structure (project verification)€50
Notification of an alteration or maintenance of a residential building€150
Landscaping or external works on notification€50
Minor structure or alteration referred to building intent proceedings after notification€100
Final approval certificate30% of the intent rate (family house €90)
Repeated final approval inspection20% of the rate (family house €60)
Change of the building intent decision€150
Extension of the verification clause's validity€100
If the office misses the statutory deadline, it refunds the fee (položka 59, poznámka 2). Holders of a ŤZP card (severe disability) are exempt from the intent fee for alterations of residential buildings. On top of administrative fees, the municipality may charge a local development fee (miestny poplatok za rozvoj) - proof of payment is attached to the final approval application (§ 66 ods. 2 písm. l)). The rates also apply from 1 Jan 2027.

Source: Act No. 145/1995 Z. z. on Administrative Fees (položka 59), Act No. 25/2025 Z. z., Building Act (Stavebný zákon)

Deadlines and validity

WhatDeadline§
Binding opinion of an authority30 days (60 for complex structures), then "no comments"§ 21 ods. 9
Request to complete the applicationwithin 15 days§ 50 ods. 3
Decision on the building intent30 days without a hearing, 60 days with a hearing, 90 days for complex structures§ 58
Appeal15 days§ 54 Správneho poriadku
Verification of the building project30 days§ 65
Notification30 days, then the project is deemed verified§ 63 ods. 6, 7
Final approval inspectionnotice within 7 working days, inspection within 30 days§ 66 ods. 3
Final approval certificatewithin 15 days of the inspection§ 66 ods. 7
Validity of the building intent decision2 years (extension by up to 2 years, 7 years in total at most)§ 61, § 62 ods. 3
Start of construction after project verificationwithin 2 years§ 65 ods. 6
Start of notified workswithin 3 years§ 63 ods. 10
The intent decision does not expire if you apply for project verification within the 2 years (§ 61 ods. 1).

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 71/1967 Zb., Administrative Procedure Code (Správny poriadok)

Self-build and who manages the works

  • A family house yourself. You can build it if it is a simple structure and the works are managed by a person authorised for construction supervision (stavebný dozor) (§ 26 ods. 3).
  • Minor structures and alterations. Minor structures, alterations and maintenance on notification can be done yourself if professional guidance is provided by a person with construction (mechanical, electrical) education and practice under § 26 ods. 3.
  • Otherwise a contractor. The works must be carried out by an authorised contractor (oprávnený zhotoviteľ) (§ 26 ods. 2).
  • Fine. Self-building without construction supervision risks a fine of up to €3,000 (§ 79 ods. 2 písm. b)).

Do you offer construction or renovation work? Post a listing in the Repair & Renovation category on OZNA.SK. Repair & Renovation →

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)

Final approval

  • When. For a new structure, a change to a completed structure (extension, added storey) and landscaping that required a building intent decision. Not required for notified structures and alterations (§ 66 ods. 1).
  • Attachments to the application. Depending on the structure: construction log, final statement of the site manager (stavbyvedúci), as-built documentation, surveying documentation and a geometric plan (geometrický plán), inspection reports (electricity, gas), the building's energy performance certificate, binding opinions for final approval, proof of payment of the local development fee (§ 66 ods. 2).
  • Procedure. Within 7 working days the office sets the inspection date, and the inspection takes place within 30 days. If everything is fine, it issues the final approval certificate within 15 days; defects must be removed within the set deadline (§ 66 ods. 3 - 7).
  • Final approval certificate. It confirms that the structure is fit for its designed purpose; you may use it only for the purpose stated in it (§ 67, § 68 ods. 1).
  • Without final approval. Using a structure without the certificate is an offence with a fine of up to €15,000 (§ 79 ods. 3 písm. c)). An unapproved structure also complicates a sale, a mortgage and registration in the land registry.
  • Tax. After final approval, file a property tax return by 31 January of the following year - in 2027 by 1 Feb, because 31 Jan falls on a Sunday.

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)

Unauthorised construction and fines

A structure without a verified project (or deviating from it) is unauthorised (čierna stavba). The building inspectorate (stavebný inšpektorát) can impose a fine and order the removal of the structure at your expense (§ 78, § 79).

Minor structure or alteration on notification without a verified project

Until 31 Dec 2026
€30 - 3,000
From 1 Jan 2027
€30 - 3,000

Self-build without construction supervision

Until 31 Dec 2026
€30 - 3,000
From 1 Jan 2027
€30 - 3,000

Structure without a verified project or deviating from it

Until 31 Dec 2026
€30 - 15,000
From 1 Jan 2027
€300 - 15,000

Using a structure without a final approval certificate

Until 31 Dec 2026
€30 - 15,000
From 1 Jan 2027
€300 - 15,000

Self-build in a protected area or on land excluded from development

Until 31 Dec 2026
€30 - 200,000
From 1 Jan 2027
€100 - 30,000
For a repeat offence within 3 years the fine can be doubled (§ 79 ods. 7; from 2027 ods. 6).

Retroactive permit

  • Structures built by 31 Mar 2025. Retroactive permit (dodatočné povolenie) under the old Act 50/1976 - application by 31 Mar 2029, from 1 Jan 2027 by 31 Dec 2040. Within the same period you can apply for a review of the structure's fitness for use (preskúmanie spôsobilosti stavby na užívanie - for older structures without final approval) (§ 84 ods. 7).
  • Structures from 1 Apr 2025 - 31 Dec 2026. Until the end of 2026 the new law does not allow them to be legalised. From 1 Jan 2027 they can be authorised by a building intent decision, but only the listed types - e.g. an extension or added storey of a family house, a garage, a carport, a pool, a retaining wall, a fence, paved areas, utility connections (§ 18 ods. 2, § 60 ods. 4 as amended). As-built documentation is attached to the application (§ 50 ods. 3 as amended).
  • The fine remains. Legalisation does not remove liability for the offence (§ 60 ods. 7 as amended).

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)

Started under the old law?

  • An application or proceedings started by 31 Mar 2025 are completed under the old law (§ 84 ods. 4).
  • Do you have a zoning decision (územné rozhodnutie) under the old law? You will still obtain the building permit and the final approval decision under the old law (§ 84 ods. 5).
  • Do you have a building permit under the old law? A change to the structure, early use and the final approval decision are handled under the old law (§ 84 ods. 6).
  • Deadlines from decisions under the old law keep running until they expire (§ 84 ods. 3).

Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)

What changes from 1 Jan 2027

Notification of minor structures

Until 31 Dec 2026
single-storey and underground minor structures - always
From 1 Jan 2027
only under the conditions of § 18 ods. 3 (e.g. solid foundation, closer than 2 m to the boundary)

Fence as a minor structure

Until 31 Dec 2026
up to 1.6 m (opaque) / 2 m (see-through)
From 1 Jan 2027
up to 2 m of any material

Outdoor charging station

Until 31 Dec 2026
minor structure up to 22 kW
From 1 Jan 2027
always a notification

Final approval

Until 31 Dec 2026
new structure, change to a structure, landscaping after a building intent
From 1 Jan 2027
also alterations and maintenance after a building intent; if the intent was required after a notification, the office may waive final approval

Appeal against the final approval certificate

Until 31 Dec 2026
the certificate is a special document, not a decision
From 1 Jan 2027
the law says explicitly: no appeal

Unauthorised structures 1 Apr 2025 - 31 Dec 2026

Until 31 Dec 2026
cannot be legalised
From 1 Jan 2027
legalisation via building intent (selected types)

Deadline to legalise old structures

Until 31 Dec 2026
by 31 Mar 2029
From 1 Jan 2027
by 31 Dec 2040

Minimum fine - structure without a verified project

Until 31 Dec 2026
€30
From 1 Jan 2027
€300

According to the ministry, amendment No. 243/2026 Z. z. does not change the substance of the rules but clarifies definitions and procedures. Fees stay the same.

Source: Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027), Act No. 145/1995 Z. z. on Administrative Fees (položka 59)

Common mistakes

  • Looking for a "building permit" form - today you apply for a building intent decision or file a notification.
  • Starting construction before the project is verified - even with a final intent decision you need a verified project; otherwise it is unauthorised construction.
  • Building a garage or fence right at the boundary without notification - closer than 2 m to the plot boundary means a notification.
  • Moving in before final approval - a fine of up to €15,000 and problems with a sale or mortgage.
  • Letting validity lapse - the intent is valid for 2 years, a verified project must be started within 2 years, notified works within 3 years.

Checklist before you build

  1. Title deed (list vlastníctva) for the plot - check the owner, encumbrances and easements.
  2. Municipal zoning plan (územný plán) - whether the plot is designated for development.
  3. Designer (authorised for a house) and surveyor.
  4. Binding opinions of authorities and statements of utility operators (water, sewage, electricity, gas).
  5. Building intent and building project, or project for notification.
  6. Authorised contractor or construction supervision for a self-build.
  7. Construction log and verified project on site.
  8. Documents for final approval: inspection reports, energy performance certificate, geometric plan.
How to read a title deed →

FAQ

Does the building permit still exist?

Not in its original form. Since 1 Apr 2025 it has been replaced by the decision on the building intent and verification of the building project. Permits issued under the old law remain valid.

Do I need a permit for a garage?

A garage up to 50 m² and 5 m high is a minor structure. Until the end of 2026 it always requires a notification; from 1 Jan 2027 only under the conditions of § 18 ods. 3 - e.g. if it has a solid foundation or stands closer than 2 m to the plot boundary. A larger garage needs a building intent.

Do I need a permit for a fence?

A fence is a minor structure (from 2027 up to 2 m high). A notification is needed if it stands closer than 2 m to the plot boundary or next to a public space - so for an ordinary boundary fence almost always.

How much does a permit for a family house cost?

Administrative fees: €300 for the building intent decision, €90 for project verification (if submitted with the intent, otherwise €150) and €90 for the final approval certificate. Plus the costs of the designer, surveyor and opinions.

How long does it take?

The intent decision within 30 days (60 with a hearing), project verification within 30 days, a notification within 30 days. Add the time to prepare the project and obtain the authorities' opinions (30 - 60 days).

Do I need a permit to renovate a flat?

Replacing tiles, floors, the kitchen, bath, toilet or windows and painting need nothing. Work on load-bearing structures must be notified, and the office may require building intent proceedings.

Can I live in a house without final approval?

No. A structure built on a building intent may only be used after the final approval certificate; otherwise you risk a fine of up to €15,000.

Can I build a house myself?

Yes, if it is a simple structure (a family house with up to 3 flats and 300 m²) and the works are managed by a person authorised for construction supervision.

What about an unauthorised structure?

Structures built by 31 Mar 2025 can be legalised under the old law - application by 31 Mar 2029, from 2027 by 31 Dec 2040. Structures from 2025 - 2026 can be legalised from 1 Jan 2027 via a building intent if they are among the listed types. The fine still applies.

Where do I file the application?

At the building office of the municipality where the structure will be - electronically through the information system (Portál výstavby). If the municipality has no building office of its own, the joint municipal office handles it.

Sources

Laws in their current wording on which this article is based (checked 9 Nov 2026):

More guides

The new Building Act simplified the terms, not the obligations: a house needs a building intent decision, a verified project and a final approval certificate, while smaller structures often only need a notification. Before buying a plot, check the zoning plan and the title deed, ask the building office which regime your structure falls under, and keep an eye on the changes from 1 Jan 2027. Then all that is left is finding the right plot.

Published 9 Nov 2026 · Updated 9 Nov 2026

For information only, not legal advice. Status as of 9 Nov 2026.

Looking for a plot or a house?

Browse plots and houses for sale on OZNA.SK - or post your own listing if you are selling.

Plots for sale

Houses for sale

OZNA.SK is now on iPhone

Browse listings, contact sellers and manage your own listings in the iPhone app. Free on the App Store.

More about the app →
Download the OZNA.SK app on the App Store