Building permit in Slovakia 2026: building intent, notification, final approval and 2027 changes
Since 1 Apr 2025 Slovakia has a new Building Act - the building permit (stavebné povolenie) was replaced by a building intent decision and project verification. An amendment follows on 1 Jan 2027. We explain what you need for a house, garage, fence or flat renovation, what it costs and how long it takes. Every rule is linked to the law.

What changed - a building intent instead of a building permit
The old Building Act No. 50/1976 Zb. applied for almost 50 years. The new Act No. 25/2025 Z. z. has been in force since 1 April 2025 and changes the whole procedure:
- One procedure instead of two. The zoning decision and the building permit are no longer two separate proceedings. A single decision on the building intent sites and authorises the structure; the office then verifies the project with a verification clause (overovacia doložka) (§ 18 ods. 2, § 65).
- New terms. Zoning proceedings (územné konanie) = building intent proceedings, building proceedings (stavebné konanie) = verification of the building project, final approval proceedings = final approval (kolaudácia) (§ 84 ods. 11).
- Final approval certificate. The final approval decision (kolaudačné rozhodnutie) was replaced by a final approval certificate (kolaudačné osvedčenie) (§ 67).
- The building office is the municipality. It is delegated state administration; municipalities may run a joint office (spoločný obecný úrad) (§ 15).
- Electronically. Documentation is prepared and stored in the information system of the Office for Spatial Planning and Construction (§ 8 ods. 3); the application is filed electronically on the prescribed form (§ 50 ods. 1).
- Opinions first. The builder or designer obtains the binding opinions of authorities and utility operators (záväzné stanoviská) before filing the application (§ 20).
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Portál výstavby (Office for Spatial Planning and Construction of the SR)
Three regimes: building intent, notification, no permit
Decision on the building intent
- For what
- new structures (incl. a family house), extensions, added storeys, larger structures; everything the law does not exempt
- Documentation
- building intent and building project by an authorised designer
- Office deadline
- 30 / 60 / 90 days
- Final approval
- yes
- Fee
- family house: €300 + verification €90 - 150 + final approval €90
Notification (ohlásenie)
- For what
- minor structures and building alterations under the conditions of § 18 ods. 3 and structures under § 18 ods. 4
- Documentation
- building project for notification
- Office deadline
- 30 days, then "tacit consent"
- Final approval
- no (with exceptions)
- Fee
- €50 (minor structure), €150 (alteration of a residential building)
Nothing needed
- For what
- routine maintenance, replacing fixtures and built-in furniture, other minor structures and alterations (§ 18 ods. 5)
- Documentation
- -
- Office deadline
- -
- Final approval
- no
- Fee
- €0
| Regime | Decision on the building intent | Notification (ohlásenie) | Nothing needed |
|---|---|---|---|
| For what | new structures (incl. a family house), extensions, added storeys, larger structures; everything the law does not exempt | minor structures and building alterations under the conditions of § 18 ods. 3 and structures under § 18 ods. 4 | routine maintenance, replacing fixtures and built-in furniture, other minor structures and alterations (§ 18 ods. 5) |
| Documentation | building intent and building project by an authorised designer | building project for notification | - |
| Office deadline | 30 / 60 / 90 days | 30 days, then "tacit consent" | - |
| Final approval | yes | no (with exceptions) | no |
| Fee | family house: €300 + verification €90 - 150 + final approval €90 | €50 (minor structure), €150 (alteration of a residential building) | €0 |
Minor and simple structure
- Minor structure (drobná stavba). Cannot significantly affect its surroundings: mainly single-storey structures up to 50 m² and 5 m high (shed, summer kitchen, carport, sauna, garage), underground structures up to 25 m² and 3 m deep (cellar, cesspit, pool), fencing, utility connections (§ 2 ods. 4; from 2027 § 2 ods. 7).
- Simple structure (jednoduchá stavba). Has no major impact on its surroundings: mainly a residential building with at most 3 flats, a built-up area up to 300 m² and at most 2 above-ground storeys (+ a basement and an attic) - i.e. an ordinary family house; a holiday cottage up to 300 m² with one above-ground storey; a retaining wall up to 3 m (§ 2 ods. 6).
- Self-build. You can build a simple structure yourself (svojpomoc) - see the conditions in the self-build section below.
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027), Act No. 145/1995 Z. z. on Administrative Fees (položka 59)
What do I need for…
Family house (up to 3 flats, 300 m²)
- Until 31 Dec 2026
- building intent + project verification + final approval
- From 1 Jan 2027
- no change
Extension, added storey, attic conversion
- Until 31 Dec 2026
- building intent (change to a completed structure) + final approval
- From 1 Jan 2027
- no change
Garage, shed, summer kitchen up to 50 m²
- Until 31 Dec 2026
- always a notification
- From 1 Jan 2027
- notification if it has a solid foundation, stands closer than 2 m to the plot boundary or another condition of § 18 ods. 3 applies; otherwise nothing
Fence
- Until 31 Dec 2026
- notification if closer than 2 m to the plot boundary or next to a public space (minor structure up to 1.6 m opaque / 2 m see-through)
- From 1 Jan 2027
- the same, minor structure up to 2 m of any material
In-ground pool, cellar, cesspit up to 25 m²
- Until 31 Dec 2026
- notification
- From 1 Jan 2027
- notification (underground structure)
Flat renovation - tiles, floors, kitchen, bath, toilet, painting, windows
- Until 31 Dec 2026
- nothing
- From 1 Jan 2027
- nothing
Work on load-bearing structures, new openings in walls
- Until 31 Dec 2026
- notification; the office may require building intent proceedings
- From 1 Jan 2027
- the same; if building intent proceedings are required, final approval follows
Façade repair, roof covering replacement
- Until 31 Dec 2026
- nothing (unless it is a cultural monument)
- From 1 Jan 2027
- nothing; in a heritage area a notification if the appearance changes
Solar panels up to 50 kW
- Until 31 Dec 2026
- nothing
- From 1 Jan 2027
- nothing
Outdoor EV charging station
- Until 31 Dec 2026
- up to 22 kW: notification only if a condition of § 18 ods. 3 applies
- From 1 Jan 2027
- always a notification
The conditions of § 18 ods. 3 that trigger a notification: works in a public space, a structure closer than 2 m to the plot boundary, a structure with a registration number (súpisné číslo), a building with a solid foundation, an underground structure, a cultural monument, a heritage or protected area, a risk to health, structural stability or fire safety, a riverside plot, a floodplain or a water source protection zone. If unsure, ask the building office before you start.
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)
Building intent step by step
From the project to the final approval certificate - the usual order for a family house or an extension.
The designer prepares the building intent
For a family house this is an authorised designer (chartered architect or engineer); without a designer the office rejects the application (§ 59 ods. 1 písm. b)).
Consultation on the intent
The designer uploads the documentation to the information system and asks the spatial planning authority, the authorities concerned and the utility operators for binding opinions and statements. They have 30 days (60 for complex structures); if they miss the deadline, they are deemed to have no comments (§ 20, § 21 ods. 9). The result is the report on the consultation of the building intent (správa o prerokovaní).
Application to the building office
Electronically on the form, with the project documentation and the consultation report (§ 50). If anything is missing, the office asks you within 15 days to complete it (§ 50 ods. 3).
Proceedings and decision
Within 7 days the office notifies the owners of neighbouring plots and other parties that proceedings have started; objections can be raised at the latest at the oral hearing or, if there is none, within at least 7 working days (§ 49, § 51). The decision comes within 30 days if no hearing is needed, otherwise within 60 days (§ 58). The decision can be appealed within 15 days (§ 54 of the Administrative Procedure Code).
Verification of the building project
The office verifies the detailed project with compliance clauses (doložky súladu) within 30 days (§ 65). You can also submit the project together with the intent - it is then verified together with the decision, and the fee is lower.
Construction
The verified project and the construction log (stavebný denník) must be kept on site (§ 6 ods. 5); in the decision the office sets the stages at which it carries out a check inspection (§ 60 ods. 1 písm. g)). Construction must start within 2 years of the project's verification (§ 65 ods. 6).
Final approval
After completion you file an application for final approval and after the inspection receive the final approval certificate (§ 66, § 67). Only then may you use the house; after final approval, remember to file a property tax return.
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 71/1967 Zb., Administrative Procedure Code (Správny poriadok), Portál výstavby (Office for Spatial Planning and Construction of the SR)
Notification of a minor structure or building alteration
- What you file. A notification with the builder's details, land registry data on the plot and the type of works; attached are the building project for notification and the binding opinions of the authorities concerned (§ 63 ods. 2).
- Who draws the project. It does not have to be an authorised designer - a person with a university degree in architecture, civil, mechanical or electrical engineering, or with secondary vocational education in these fields and at least 3 years of practice, is enough (§ 35 ods. 4, 5).
- 30-day deadline. The office verifies the project with a clause or returns the notification. If it does nothing within the deadline, the clause is deemed issued (§ 63 ods. 6, 7).
- The office may decide otherwise. If the structure would affect neighbours' rights or conditions need to be set, it tells you that building intent proceedings are required (§ 63 ods. 5).
- Returned notification. A return can be challenged by a complaint (podnet) within 10 working days (§ 63 ods. 8).
- Start within 3 years. The notified works must start within 3 years of the project's verification (§ 63 ods. 10).
- No final approval. Final approval is generally not required for notified structures and alterations (§ 66 ods. 1).
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)
Fees 2026
| Act | Fee |
|---|---|
| Decision on the building intent - family house (1 - 2 flats) | €300 |
| Decision on the building intent - simple non-residential structure (e.g. a larger garage) | €300 |
| Extension, added storey or demolition | 25% of the rate (family house €75) |
| Project verification together with the intent | 30% of the rate (family house €90) |
| Project verification separately | 50% of the rate (family house €150) |
| Notification of a minor structure (project verification) | €50 |
| Notification of an alteration or maintenance of a residential building | €150 |
| Landscaping or external works on notification | €50 |
| Minor structure or alteration referred to building intent proceedings after notification | €100 |
| Final approval certificate | 30% of the intent rate (family house €90) |
| Repeated final approval inspection | 20% of the rate (family house €60) |
| Change of the building intent decision | €150 |
| Extension of the verification clause's validity | €100 |
If the office misses the statutory deadline, it refunds the fee (položka 59, poznámka 2). Holders of a ŤZP card (severe disability) are exempt from the intent fee for alterations of residential buildings. On top of administrative fees, the municipality may charge a local development fee (miestny poplatok za rozvoj) - proof of payment is attached to the final approval application (§ 66 ods. 2 písm. l)). The rates also apply from 1 Jan 2027.
Source: Act No. 145/1995 Z. z. on Administrative Fees (položka 59), Act No. 25/2025 Z. z., Building Act (Stavebný zákon)
Deadlines and validity
| What | Deadline | § |
|---|---|---|
| Binding opinion of an authority | 30 days (60 for complex structures), then "no comments" | § 21 ods. 9 |
| Request to complete the application | within 15 days | § 50 ods. 3 |
| Decision on the building intent | 30 days without a hearing, 60 days with a hearing, 90 days for complex structures | § 58 |
| Appeal | 15 days | § 54 Správneho poriadku |
| Verification of the building project | 30 days | § 65 |
| Notification | 30 days, then the project is deemed verified | § 63 ods. 6, 7 |
| Final approval inspection | notice within 7 working days, inspection within 30 days | § 66 ods. 3 |
| Final approval certificate | within 15 days of the inspection | § 66 ods. 7 |
| Validity of the building intent decision | 2 years (extension by up to 2 years, 7 years in total at most) | § 61, § 62 ods. 3 |
| Start of construction after project verification | within 2 years | § 65 ods. 6 |
| Start of notified works | within 3 years | § 63 ods. 10 |
The intent decision does not expire if you apply for project verification within the 2 years (§ 61 ods. 1).
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 71/1967 Zb., Administrative Procedure Code (Správny poriadok)
Self-build and who manages the works
- A family house yourself. You can build it if it is a simple structure and the works are managed by a person authorised for construction supervision (stavebný dozor) (§ 26 ods. 3).
- Minor structures and alterations. Minor structures, alterations and maintenance on notification can be done yourself if professional guidance is provided by a person with construction (mechanical, electrical) education and practice under § 26 ods. 3.
- Otherwise a contractor. The works must be carried out by an authorised contractor (oprávnený zhotoviteľ) (§ 26 ods. 2).
- Fine. Self-building without construction supervision risks a fine of up to €3,000 (§ 79 ods. 2 písm. b)).
Do you offer construction or renovation work? Post a listing in the Repair & Renovation category on OZNA.SK. Repair & Renovation →
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)
Final approval
- When. For a new structure, a change to a completed structure (extension, added storey) and landscaping that required a building intent decision. Not required for notified structures and alterations (§ 66 ods. 1).
- Attachments to the application. Depending on the structure: construction log, final statement of the site manager (stavbyvedúci), as-built documentation, surveying documentation and a geometric plan (geometrický plán), inspection reports (electricity, gas), the building's energy performance certificate, binding opinions for final approval, proof of payment of the local development fee (§ 66 ods. 2).
- Procedure. Within 7 working days the office sets the inspection date, and the inspection takes place within 30 days. If everything is fine, it issues the final approval certificate within 15 days; defects must be removed within the set deadline (§ 66 ods. 3 - 7).
- Final approval certificate. It confirms that the structure is fit for its designed purpose; you may use it only for the purpose stated in it (§ 67, § 68 ods. 1).
- Without final approval. Using a structure without the certificate is an offence with a fine of up to €15,000 (§ 79 ods. 3 písm. c)). An unapproved structure also complicates a sale, a mortgage and registration in the land registry.
- Tax. After final approval, file a property tax return by 31 January of the following year - in 2027 by 1 Feb, because 31 Jan falls on a Sunday.
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)
Unauthorised construction and fines
A structure without a verified project (or deviating from it) is unauthorised (čierna stavba). The building inspectorate (stavebný inšpektorát) can impose a fine and order the removal of the structure at your expense (§ 78, § 79).
Minor structure or alteration on notification without a verified project
- Until 31 Dec 2026
- €30 - 3,000
- From 1 Jan 2027
- €30 - 3,000
Self-build without construction supervision
- Until 31 Dec 2026
- €30 - 3,000
- From 1 Jan 2027
- €30 - 3,000
Structure without a verified project or deviating from it
- Until 31 Dec 2026
- €30 - 15,000
- From 1 Jan 2027
- €300 - 15,000
Using a structure without a final approval certificate
- Until 31 Dec 2026
- €30 - 15,000
- From 1 Jan 2027
- €300 - 15,000
Self-build in a protected area or on land excluded from development
- Until 31 Dec 2026
- €30 - 200,000
- From 1 Jan 2027
- €100 - 30,000
For a repeat offence within 3 years the fine can be doubled (§ 79 ods. 7; from 2027 ods. 6).
Retroactive permit
- Structures built by 31 Mar 2025. Retroactive permit (dodatočné povolenie) under the old Act 50/1976 - application by 31 Mar 2029, from 1 Jan 2027 by 31 Dec 2040. Within the same period you can apply for a review of the structure's fitness for use (preskúmanie spôsobilosti stavby na užívanie - for older structures without final approval) (§ 84 ods. 7).
- Structures from 1 Apr 2025 - 31 Dec 2026. Until the end of 2026 the new law does not allow them to be legalised. From 1 Jan 2027 they can be authorised by a building intent decision, but only the listed types - e.g. an extension or added storey of a family house, a garage, a carport, a pool, a retaining wall, a fence, paved areas, utility connections (§ 18 ods. 2, § 60 ods. 4 as amended). As-built documentation is attached to the application (§ 50 ods. 3 as amended).
- The fine remains. Legalisation does not remove liability for the offence (§ 60 ods. 7 as amended).
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon), Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)
Started under the old law?
- An application or proceedings started by 31 Mar 2025 are completed under the old law (§ 84 ods. 4).
- Do you have a zoning decision (územné rozhodnutie) under the old law? You will still obtain the building permit and the final approval decision under the old law (§ 84 ods. 5).
- Do you have a building permit under the old law? A change to the structure, early use and the final approval decision are handled under the old law (§ 84 ods. 6).
- Deadlines from decisions under the old law keep running until they expire (§ 84 ods. 3).
Source: Act No. 25/2025 Z. z., Building Act (Stavebný zákon)
What changes from 1 Jan 2027
Notification of minor structures
- Until 31 Dec 2026
- single-storey and underground minor structures - always
- From 1 Jan 2027
- only under the conditions of § 18 ods. 3 (e.g. solid foundation, closer than 2 m to the boundary)
Fence as a minor structure
- Until 31 Dec 2026
- up to 1.6 m (opaque) / 2 m (see-through)
- From 1 Jan 2027
- up to 2 m of any material
Outdoor charging station
- Until 31 Dec 2026
- minor structure up to 22 kW
- From 1 Jan 2027
- always a notification
Final approval
- Until 31 Dec 2026
- new structure, change to a structure, landscaping after a building intent
- From 1 Jan 2027
- also alterations and maintenance after a building intent; if the intent was required after a notification, the office may waive final approval
Appeal against the final approval certificate
- Until 31 Dec 2026
- the certificate is a special document, not a decision
- From 1 Jan 2027
- the law says explicitly: no appeal
Unauthorised structures 1 Apr 2025 - 31 Dec 2026
- Until 31 Dec 2026
- cannot be legalised
- From 1 Jan 2027
- legalisation via building intent (selected types)
Deadline to legalise old structures
- Until 31 Dec 2026
- by 31 Mar 2029
- From 1 Jan 2027
- by 31 Dec 2040
Minimum fine - structure without a verified project
- Until 31 Dec 2026
- €30
- From 1 Jan 2027
- €300
According to the ministry, amendment No. 243/2026 Z. z. does not change the substance of the rules but clarifies definitions and procedures. Fees stay the same.
Source: Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027), Act No. 145/1995 Z. z. on Administrative Fees (položka 59)
Common mistakes
- Looking for a "building permit" form - today you apply for a building intent decision or file a notification.
- Starting construction before the project is verified - even with a final intent decision you need a verified project; otherwise it is unauthorised construction.
- Building a garage or fence right at the boundary without notification - closer than 2 m to the plot boundary means a notification.
- Moving in before final approval - a fine of up to €15,000 and problems with a sale or mortgage.
- Letting validity lapse - the intent is valid for 2 years, a verified project must be started within 2 years, notified works within 3 years.
Checklist before you build
- Title deed (list vlastníctva) for the plot - check the owner, encumbrances and easements.
- Municipal zoning plan (územný plán) - whether the plot is designated for development.
- Designer (authorised for a house) and surveyor.
- Binding opinions of authorities and statements of utility operators (water, sewage, electricity, gas).
- Building intent and building project, or project for notification.
- Authorised contractor or construction supervision for a self-build.
- Construction log and verified project on site.
- Documents for final approval: inspection reports, energy performance certificate, geometric plan.
FAQ
Does the building permit still exist?
Not in its original form. Since 1 Apr 2025 it has been replaced by the decision on the building intent and verification of the building project. Permits issued under the old law remain valid.
Do I need a permit for a garage?
A garage up to 50 m² and 5 m high is a minor structure. Until the end of 2026 it always requires a notification; from 1 Jan 2027 only under the conditions of § 18 ods. 3 - e.g. if it has a solid foundation or stands closer than 2 m to the plot boundary. A larger garage needs a building intent.
Do I need a permit for a fence?
A fence is a minor structure (from 2027 up to 2 m high). A notification is needed if it stands closer than 2 m to the plot boundary or next to a public space - so for an ordinary boundary fence almost always.
How much does a permit for a family house cost?
Administrative fees: €300 for the building intent decision, €90 for project verification (if submitted with the intent, otherwise €150) and €90 for the final approval certificate. Plus the costs of the designer, surveyor and opinions.
How long does it take?
The intent decision within 30 days (60 with a hearing), project verification within 30 days, a notification within 30 days. Add the time to prepare the project and obtain the authorities' opinions (30 - 60 days).
Do I need a permit to renovate a flat?
Replacing tiles, floors, the kitchen, bath, toilet or windows and painting need nothing. Work on load-bearing structures must be notified, and the office may require building intent proceedings.
Can I live in a house without final approval?
No. A structure built on a building intent may only be used after the final approval certificate; otherwise you risk a fine of up to €15,000.
Can I build a house myself?
Yes, if it is a simple structure (a family house with up to 3 flats and 300 m²) and the works are managed by a person authorised for construction supervision.
What about an unauthorised structure?
Structures built by 31 Mar 2025 can be legalised under the old law - application by 31 Mar 2029, from 2027 by 31 Dec 2040. Structures from 2025 - 2026 can be legalised from 1 Jan 2027 via a building intent if they are among the listed types. The fine still applies.
Where do I file the application?
At the building office of the municipality where the structure will be - electronically through the information system (Portál výstavby). If the municipality has no building office of its own, the joint municipal office handles it.
Sources
Laws in their current wording on which this article is based (checked 9 Nov 2026):
- Act No. 25/2025 Z. z., Building Act (Stavebný zákon)
- Act No. 243/2026 Z. z. (amendment to the Building Act from 1 Jan 2027)
- Act No. 145/1995 Z. z. on Administrative Fees (položka 59)
- Act No. 71/1967 Zb., Administrative Procedure Code (Správny poriadok)
- Portál výstavby (Office for Spatial Planning and Construction of the SR)
More guides
Title deed and land registry →
How to find the plot owner, encumbrances, easements and a pending-change flag.
Property tax 2026 →
Who files a return, deadlines, rates and what to do after a house gets final approval.
Mortgage for young people 2026 →
Tax bonus on interest, 90% loans from 2027 and ŠFRB loans, also for building.
The new Building Act simplified the terms, not the obligations: a house needs a building intent decision, a verified project and a final approval certificate, while smaller structures often only need a notification. Before buying a plot, check the zoning plan and the title deed, ask the building office which regime your structure falls under, and keep an eye on the changes from 1 Jan 2027. Then all that is left is finding the right plot.
Published 9 Nov 2026 · Updated 9 Nov 2026
For information only, not legal advice. Status as of 9 Nov 2026.
Looking for a plot or a house?
Browse plots and houses for sale on OZNA.SK - or post your own listing if you are selling.
Plots for saleOZNA.SK is now on iPhone
Browse listings, contact sellers and manage your own listings in the iPhone app. Free on the App Store.
More about the app →